Cost Item | Quantity | Cost/Item | Total $ | Land Purchase | | | |
Land Purchase | 1.00 Each | 2,000,000.00 | 2,000,000.00 |
Total Land Purchase | | | $2,000,000.00 |
| | | |
Construction | | | |
Construction Spending | 20,000.00 Each | 60.00 | 1,200,000.00 |
Total Construction | | | $1,200,000.00 |
| | | |
Contigency | | | |
Hard Cost Contigency | 1.00 Each | 35,000.00 | 35,000.00 |
Total Contigency | | | $35,000.00 |
| | | |
Site Work | | | |
General Conditions | 1.00 Each | 40,000.00 | 40,000.00 |
Trash Enclosures | 1.00 Each | 9,500.00 | 9,500.00 |
Clearing & Grading | 1.00 Each | 23,000.00 | 23,000.00 |
Storm Drainage | 1.00 Each | 35,000.00 | 35,000.00 |
Site Concrete | 1.00 Each | 23,000.00 | 23,000.00 |
Sub Base paving | 1.00 Each | 30,000.00 | 30,000.00 |
Building Pad stabalization | 1.00 Each | 10,000.00 | 10,000.00 |
Site Utilities | 1.00 Each | 25,000.00 | 25,000.00 |
Site Electric-Lighting | 1.00 Each | 40,000.00 | 40,000.00 |
Signage | 1.00 Each | 25,000.00 | 25,000.00 |
Landscape & Irrigation | 1.00 Each | 20,000.00 | 20,000.00 |
Contg. | 1.00 Each | 30,000.00 | 30,000.00 |
Total Site Work | | | $310,500.00 |
| | | |
Building Other | | | |
Sewer Capacity | 1.00 Each | 5,000.00 | 5,000.00 |
Water Fee's | 1.00 Each | 2,000.00 | 2,000.00 |
Electricial Fee's | 1.00 Each | 5,000.00 | 5,000.00 |
Permits-Zoning-Review Fee's | 1.00 Each | 3,000.00 | 3,000.00 |
Plan Copies | 1.00 Each | 500.00 | 500.00 |
Developers Liability Insurance | 1.00 Each | 12,000.00 | 12,000.00 |
Total Building Other | | | $27,500.00 |
| | | |
Architectuaancemp; Engineering | | | |
Architects | 20,000.00 SqFt | 3.25 | 65,000.00 |
Civil Engineering | 1.00 Each | 22,000.00 | 22,000.00 |
Landscape Design | 1.00 Each | 2,500.00 | 2,500.00 |
Reimbursable Architects | 1.00 Each | 4,500.00 | 4,500.00 |
Total Architectual & Engineering | | | $94,000.00 |
| | | |
Soft Costs | | | |
Legal | 1.00 Each | 45,000.00 | 45,000.00 |
Travel to site | 1.00 Each | 800.00 | 800.00 |
Construction Management Fee | 1.00 Each | 7,500.00 | 7,500.00 |
Appraisal | 1.00 Each | 4,500.00 | 4,500.00 |
Survey | 1.00 Each | 3,500.00 | 3,500.00 |
Title Insurance | 1.00 Each | 3,500.00 | 3,500.00 |
Total Soft Costs | | | $64,800.00 |
| | | |
Contigency | | | |
General Contigency | 1.00 Each | 30,000.00 | 30,000.00 |
Total Contigency | | | $30,000.00 |
| | | |
Tenant & Leasing Costs | | | |
TI for First Floor | 20,000.00 SqFt | 25.00 | 500,000.00 |
Commisions for First Floor | 20,000.00 Each | 6.00 | 120,000.00 |
Total Tenant & Leasing Costs | | | $620,000.00 |
| | | |
Total Project Cost | | | $4,381,800.00 |
|