Date | Cost Item | Quantity | Cost/Item | Total $ | Feb 12 | Land | 1.00 Each | $1,050,000 | $1,050,000 |
Feb 12 | Clearing & Grading (Spread over 2 Mos) | N/A | $59,429 | 29,715 |
Feb 12 | Contingency | 1.00 Each | $35,000 | 35,000 |
Feb 12 | Design (Spread over 3 Mos) | N/A | $37,500 | 12,500 |
Feb 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Feb 12 | Legal & Closing | 1.00 Each | $13,000 | 13,000 |
Feb 12 | Appraisal | 1.00 Each | $5,000 | 5,000 |
Feb 12 | County Fees | 1.00 Each | $2,000 | 2,000 |
Feb 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $1,153,215 |
| | | | |
Mar 12 | Clearing & Grading (Spread over 2 Mos) | N/A | $59,429 | $29,715 |
Mar 12 | Design (Spread over 3 Mos) | N/A | $37,500 | 12,500 |
Mar 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Mar 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $48,215 |
| | | | |
Apr 12 | Sanitary Sewer (Spread over 3 Mos) | N/A | $160,554 | $53,518 |
Apr 12 | Storm Sewer (Spread over 3 Mos) | N/A | $61,950 | 20,650 |
Apr 12 | Power & Street Lighting | 1.00 Each | $9,402 | 9,402 |
Apr 12 | Design (Spread over 3 Mos) | N/A | $37,500 | 12,500 |
Apr 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Apr 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $102,070 |
| | | | |
May 12 | Sanitary Sewer (Spread over 3 Mos) | N/A | $160,554 | $53,518 |
May 12 | Storm Sewer (Spread over 3 Mos) | N/A | $61,950 | 20,650 |
May 12 | Water | 1.00 Each | $65,006 | 65,006 |
May 12 | Layout (Spread over 3 Mos) | N/A | $25,552 | 8,517 |
May 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
May 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $153,691 |
| | | | |
Jun 12 | Sanitary Sewer (Spread over 3 Mos) | N/A | $160,554 | $53,518 |
Jun 12 | Storm Sewer (Spread over 3 Mos) | N/A | $61,950 | 20,650 |
Jun 12 | Layout (Spread over 3 Mos) | N/A | $25,552 | 8,517 |
Jun 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Jun 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $88,685 |
| | | | |
Jul 12 | Paving (Spread over 2 Mos) | N/A | $119,663 | $59,831 |
Jul 12 | Curb & Gutter (Spread over 2 Mos) | N/A | $67,100 | 33,550 |
Jul 12 | Layout (Spread over 3 Mos) | N/A | $25,552 | 8,517 |
Jul 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Jul 12 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | 4,266 |
Jul 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $112,164 |
| | | | |
Aug 12 | Paving (Spread over 2 Mos) | N/A | $119,663 | $59,831 |
Aug 12 | Curb & Gutter (Spread over 2 Mos) | N/A | $67,100 | 33,550 |
Aug 12 | Entrance (Spread over 2 Mos) | N/A | $38,020 | 19,010 |
Aug 12 | Amenity (Spread over 5 Mos) | N/A | $285,150 | 57,030 |
Aug 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Aug 12 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | 4,266 |
Aug 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $179,687 |
| | | | |
Sep 12 | Entrance (Spread over 2 Mos) | N/A | $38,020 | $19,010 |
Sep 12 | Amenity (Spread over 5 Mos) | N/A | $285,150 | 57,030 |
Sep 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Sep 12 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | 4,266 |
Sep 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $86,306 |
| | | | |
Oct 12 | Amenity (Spread over 5 Mos) | N/A | $285,150 | $57,030 |
Oct 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Oct 12 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | 4,266 |
Oct 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $67,296 |
| | | | |
Nov 12 | Amenity (Spread over 5 Mos) | N/A | $285,150 | $57,030 |
Nov 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Nov 12 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | 4,266 |
Nov 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $67,296 |
| | | | |
Dec 12 | Amenity (Spread over 5 Mos) | N/A | $285,150 | $57,030 |
Dec 12 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | 1,000 |
Dec 12 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | 4,266 |
Dec 12 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $67,296 |
| | | | |
Jan 13 | Taxes & Insurance (Spread over 12 Mos) | N/A | $12,000 | $1,000 |
Jan 13 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | 4,266 |
Jan 13 | Development Fees (Spread over 12 Mos) | N/A | $60,000 | 5,000 |
| Total | | | $10,266 |
| | | | |
Feb 13 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | $4,266 |
| Total | | | $4,266 |
| | | | |
Mar 13 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | $4,266 |
| Total | | | $4,266 |
| | | | |
Apr 13 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | $4,266 |
| Total | | | $4,266 |
| | | | |
May 13 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | $4,266 |
| Total | | | $4,266 |
| | | | |
Jun 13 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | $4,266 |
| Total | | | $4,266 |
| | | | |
Jul 13 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | $4,266 |
| Total | | | $4,266 |
| | | | |
Aug 13 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | $4,266 |
| Total | | | $4,266 |
| | | | |
Sep 13 | Marketing & Advertising (Spread over 15 Mos) | N/A | $63,984 | $4,266 |
| Total | | | $4,266 |
| | | | |
| Total Unit Costs | | | $2,170,310 |
| | | | |
|