Date | Cost Item | Quantity | Cost/Item | Total $ | Feb 03 | Permits | 1.00 Each | $10,000 | $10,000 |
Feb 03 | Legal & Title | 1.00 Each | $18,000 | 18,000 |
| Total | | | $28,000 |
| | | | |
Mar 03 | Land | 1.00 Each | $2,850,000 | $2,850,000 |
Mar 03 | Sitework | 1.00 Each | $855,000 | 855,000 |
Mar 03 | Foundations & Floor Slab | 1.00 Each | $389,200 | 389,200 |
| Total | | | $4,094,200 |
| | | | |
Apr 03 | Structure | 1.00 Each | $266,000 | $266,000 |
| Total | | | $266,000 |
| | | | |
May 03 | Building Skin | 1.00 Each | $461,600 | $461,600 |
May 03 | Doors, Balconies | 1.00 Each | $258,800 | 258,800 |
May 03 | Exterior Contingency | 1.00 Each | $79,200 | 79,200 |
May 03 | Pool | 1.00 Each | $150,000 | 150,000 |
| Total | | | $949,600 |
| | | | |
Jun 03 | Roof Systems | 1.00 Each | $206,400 | $206,400 |
| Total | | | $206,400 |
| | | | |
Jul 03 | Electrical | 1.00 Each | $33,600 | $33,600 |
| Total | | | $33,600 |
| | | | |
Aug 03 | Landscaping | 1.00 Each | $110,400 | $110,400 |
| Total | | | $110,400 |
| | | | |
| Total Unit Costs | | | $5,688,200 |
|