Cost ItemQuantityCost/ItemTotal $
Land Purchase
Land Purchase1.00 Each2,000,000.002,000,000.00
Total Land Purchase$2,000,000.00
Construction
Construction Spending20,000.00 Each60.001,200,000.00
Total Construction$1,200,000.00
Contigency
Hard Cost Contigency1.00 Each35,000.0035,000.00
Total Contigency$35,000.00
Site Work
General Conditions1.00 Each40,000.0040,000.00
Trash Enclosures1.00 Each9,500.009,500.00
Clearing & Grading1.00 Each23,000.0023,000.00
Storm Drainage1.00 Each35,000.0035,000.00
Site Concrete1.00 Each23,000.0023,000.00
Sub Base paving1.00 Each30,000.0030,000.00
Building Pad stabalization1.00 Each10,000.0010,000.00
Site Utilities1.00 Each25,000.0025,000.00
Site Electric-Lighting1.00 Each40,000.0040,000.00
Signage1.00 Each25,000.0025,000.00
Landscape & Irrigation1.00 Each20,000.0020,000.00
Contg.1.00 Each30,000.0030,000.00
Total Site Work$310,500.00
Building Other
Sewer Capacity1.00 Each5,000.005,000.00
Water Fee's1.00 Each2,000.002,000.00
Electricial Fee's1.00 Each5,000.005,000.00
Permits-Zoning-Review Fee's1.00 Each3,000.003,000.00
Plan Copies1.00 Each500.00500.00
Developers Liability Insurance1.00 Each12,000.0012,000.00
Total Building Other$27,500.00
Architectual & Engineering
Architects20,000.00 SqFt3.2565,000.00
Civil Engineering1.00 Each22,000.0022,000.00
Landscape Design1.00 Each2,500.002,500.00
Reimbursable Architects1.00 Each4,500.004,500.00
Total Architectual & Engineering$94,000.00
Soft Costs
Legal1.00 Each45,000.0045,000.00
Travel to site1.00 Each800.00800.00
Construction Management Fee1.00 Each7,500.007,500.00
Appraisal1.00 Each4,500.004,500.00
Survey1.00 Each3,500.003,500.00
Title Insurance1.00 Each3,500.003,500.00
Total Soft Costs$64,800.00
Contigency
General Contigency1.00 Each30,000.0030,000.00
Total Contigency$30,000.00
Tenant & Leasing Costs
TI for First Floor20,000.00 SqFt25.00500,000.00
Commisions for First Floor20,000.00 Each6.00120,000.00
Total Tenant & Leasing Costs$620,000.00
Total Project Cost$4,381,800.00